PermitIndex

Reference

How long does a building permit take in Toronto?

Half of the 27,839 permits the City issued over the trailing 12 months came through within 32 days of application. One in ten took longer than 224 days. Which half you land in depends far more on what you are building than on where.

Median wait

32 days

Slowest 10%

224+ days

Permits measured

27,839

Postal areas

96

Wait time by trade

Slowest first. This is the single biggest driver of how long you will wait.

TradeMedianSlowest 10%Permits
New build65 days594 days2,946
Demolition46 days232 days1,423
Pool38 days105 days189
HVAC35 days257 days4,098
Addition34 days170 days4,680
Plumbing33 days267 days5,887
Electrical32 days94 days86
Roofing27 days120 days476
Interior alteration24 days93 days4,022
Deck21 days125 days1,384
Window / Door12 days64 days740

Wait time by postal area

The 96 Toronto postal areas with at least 30 measurable permits, slowest first.

AreaZoneMedianSlowest 10%Permits
M3CNorth York (west)233 days298 days512
M6NWest Toronto & York155 days883 days847
M6AWest Toronto & York76 days611 days477
M1LScarborough63 days259 days313
M9MEtobicoke & Northwest Toronto56 days339 days107
M2MNorth York (east)48 days150 days320
M1SScarborough45 days203 days215
M1MScarborough44 days460 days256
M1VScarborough44 days149 days160
M6MWest Toronto & York44 days296 days266
M1KScarborough43 days294 days209
M1BScarborough42 days192 days218
M1CScarborough42 days1439 days305
M2RNorth York (east)42 days267 days225
M8WEtobicoke (south)42 days135 days323
M1JScarborough39 days290 days137
M3KNorth York (west)38 days132 days98
M5ADowntown & Central Toronto38 days278 days287
M5TDowntown & Central Toronto38 days210 days264
M6BWest Toronto & York38 days167 days321
M1PScarborough36 days160 days295
M6LWest Toronto & York36 days256 days136
M1WScarborough35 days155 days131
M2KNorth York (east)35 days292 days165
M3JNorth York (west)35 days229 days148
M3NNorth York (west)35 days165 days59
M4SEast York, East Toronto & Midtown35 days148 days382
M9BEtobicoke & Northwest Toronto35 days187 days315
M9WEtobicoke & Northwest Toronto35 days165 days360
M1EScarborough34 days202 days286
M4BEast York, East Toronto & Midtown34 days156 days183
M4PEast York, East Toronto & Midtown34 days146 days225
M5CDowntown & Central Toronto34 days68 days198
M9PEtobicoke & Northwest Toronto34 days226 days107
M3LNorth York (west)33 days125 days59
M4WEast York, East Toronto & Midtown33 days168 days372
M5MDowntown & Central Toronto33 days129 days329
M3BNorth York (west)32 days137 days257
M3HNorth York (west)32 days166 days343
M4YEast York, East Toronto & Midtown32 days93 days86
M5EDowntown & Central Toronto32 days80 days79
M5SDowntown & Central Toronto32 days108 days298
M5VDowntown & Central Toronto32 days123 days398
M6EWest Toronto & York32 days186 days533
M1RScarborough31 days233 days297
M3ANorth York (west)31 days164 days136
M5JDowntown & Central Toronto31 days64 days300
M8ZEtobicoke (south)31 days238 days450
M9CEtobicoke & Northwest Toronto31 days135 days209
M9NEtobicoke & Northwest Toronto31 days387 days164
M1TScarborough30 days126 days110
M1XScarborough30 days476 days61
M2NNorth York (east)30 days113 days468
M4AEast York, East Toronto & Midtown30 days108 days102
M4HEast York, East Toronto & Midtown30 days272 days49
M5BDowntown & Central Toronto30 days121 days172
M9REtobicoke & Northwest Toronto30 days146 days104
M9VEtobicoke & Northwest Toronto30 days212 days168
M2LNorth York (east)29 days115 days145
M4VEast York, East Toronto & Midtown29 days106 days229
M6KWest Toronto & York29 days191 days351
M8YEtobicoke (south)29 days147 days226
M9LEtobicoke & Northwest Toronto29 days188 days105
M1HScarborough28 days173 days133
M1NScarborough28 days228 days292
M4CEast York, East Toronto & Midtown28 days158 days574
M4MEast York, East Toronto & Midtown28 days286 days384
M4NEast York, East Toronto & Midtown28 days211 days224
M5GDowntown & Central Toronto28 days106 days248
M5HDowntown & Central Toronto28 days63 days368
M6CWest Toronto & York28 days151 days390
M3MNorth York (west)27 days189 days107
M4EEast York, East Toronto & Midtown27 days175 days299
M5RDowntown & Central Toronto27 days116 days470
M2HNorth York (east)26 days162 days126
M4GEast York, East Toronto & Midtown26 days145 days333
M4XEast York, East Toronto & Midtown26 days97 days85
M6HWest Toronto & York26 days154 days709
M2JNorth York (east)25 days120 days221
M9AEtobicoke & Northwest Toronto25 days97 days334
M1GScarborough24 days105 days92
M4LEast York, East Toronto & Midtown24 days158 days506
M2PNorth York (east)23 days64 days91
M5PDowntown & Central Toronto23 days72 days235
M6GWest Toronto & York23 days122 days582
M6JWest Toronto & York23 days120 days553
M6SWest Toronto & York23 days112 days455
M4REast York, East Toronto & Midtown22 days140 days187
M8VEtobicoke (south)22 days139 days362
M8XEtobicoke (south)22 days205 days146
M4KEast York, East Toronto & Midtown21 days137 days460
M6PWest Toronto & York21 days160 days529
M6RWest Toronto & York19 days101 days420
M4JEast York, East Toronto & Midtown18 days111 days507
M5NDowntown & Central Toronto18 days68 days184
M4TEast York, East Toronto & Midtown15 days93 days209

Common questions

How long does a building permit take in Toronto?
Half of the 27,839 permits issued in Toronto over the last 12 months were issued within 32 days of application. One in ten took longer than 224 days. The wait varies sharply by trade: New build runs about 65 days while Window / Door runs about 12 days.
Which part of Toronto approves permits fastest?
Among the 96 postal areas with enough permits to measure, M4T has the shortest median wait at 15 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
Why is the median used instead of the average?
Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 99 days against a median of 32 days. The median is the honest answer to "how long will mine take".

How these numbers are calculated

Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.

We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 99 days against a median of 32.

One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.