How long does a building permit take in Toronto?
Half of the 27,839 permits the City issued over the trailing 12 months came through within 32 days of application. One in ten took longer than 224 days. Which half you land in depends far more on what you are building than on where.
Median wait
32 days
Slowest 10%
224+ days
Permits measured
27,839
Postal areas
96
Wait time by trade
Slowest first. This is the single biggest driver of how long you will wait.
| Trade | Median | Slowest 10% | Permits |
|---|---|---|---|
| New build | 65 days | 594 days | 2,946 |
| Demolition | 46 days | 232 days | 1,423 |
| Pool | 38 days | 105 days | 189 |
| HVAC | 35 days | 257 days | 4,098 |
| Addition | 34 days | 170 days | 4,680 |
| Plumbing | 33 days | 267 days | 5,887 |
| Electrical | 32 days | 94 days | 86 |
| Roofing | 27 days | 120 days | 476 |
| Interior alteration | 24 days | 93 days | 4,022 |
| Deck | 21 days | 125 days | 1,384 |
| Window / Door | 12 days | 64 days | 740 |
Wait time by postal area
The 96 Toronto postal areas with at least 30 measurable permits, slowest first.
| Area | Zone | Median | Slowest 10% | Permits |
|---|---|---|---|---|
| M3C | North York (west) | 233 days | 298 days | 512 |
| M6N | West Toronto & York | 155 days | 883 days | 847 |
| M6A | West Toronto & York | 76 days | 611 days | 477 |
| M1L | Scarborough | 63 days | 259 days | 313 |
| M9M | Etobicoke & Northwest Toronto | 56 days | 339 days | 107 |
| M2M | North York (east) | 48 days | 150 days | 320 |
| M1S | Scarborough | 45 days | 203 days | 215 |
| M1M | Scarborough | 44 days | 460 days | 256 |
| M1V | Scarborough | 44 days | 149 days | 160 |
| M6M | West Toronto & York | 44 days | 296 days | 266 |
| M1K | Scarborough | 43 days | 294 days | 209 |
| M1B | Scarborough | 42 days | 192 days | 218 |
| M1C | Scarborough | 42 days | 1439 days | 305 |
| M2R | North York (east) | 42 days | 267 days | 225 |
| M8W | Etobicoke (south) | 42 days | 135 days | 323 |
| M1J | Scarborough | 39 days | 290 days | 137 |
| M3K | North York (west) | 38 days | 132 days | 98 |
| M5A | Downtown & Central Toronto | 38 days | 278 days | 287 |
| M5T | Downtown & Central Toronto | 38 days | 210 days | 264 |
| M6B | West Toronto & York | 38 days | 167 days | 321 |
| M1P | Scarborough | 36 days | 160 days | 295 |
| M6L | West Toronto & York | 36 days | 256 days | 136 |
| M1W | Scarborough | 35 days | 155 days | 131 |
| M2K | North York (east) | 35 days | 292 days | 165 |
| M3J | North York (west) | 35 days | 229 days | 148 |
| M3N | North York (west) | 35 days | 165 days | 59 |
| M4S | East York, East Toronto & Midtown | 35 days | 148 days | 382 |
| M9B | Etobicoke & Northwest Toronto | 35 days | 187 days | 315 |
| M9W | Etobicoke & Northwest Toronto | 35 days | 165 days | 360 |
| M1E | Scarborough | 34 days | 202 days | 286 |
| M4B | East York, East Toronto & Midtown | 34 days | 156 days | 183 |
| M4P | East York, East Toronto & Midtown | 34 days | 146 days | 225 |
| M5C | Downtown & Central Toronto | 34 days | 68 days | 198 |
| M9P | Etobicoke & Northwest Toronto | 34 days | 226 days | 107 |
| M3L | North York (west) | 33 days | 125 days | 59 |
| M4W | East York, East Toronto & Midtown | 33 days | 168 days | 372 |
| M5M | Downtown & Central Toronto | 33 days | 129 days | 329 |
| M3B | North York (west) | 32 days | 137 days | 257 |
| M3H | North York (west) | 32 days | 166 days | 343 |
| M4Y | East York, East Toronto & Midtown | 32 days | 93 days | 86 |
| M5E | Downtown & Central Toronto | 32 days | 80 days | 79 |
| M5S | Downtown & Central Toronto | 32 days | 108 days | 298 |
| M5V | Downtown & Central Toronto | 32 days | 123 days | 398 |
| M6E | West Toronto & York | 32 days | 186 days | 533 |
| M1R | Scarborough | 31 days | 233 days | 297 |
| M3A | North York (west) | 31 days | 164 days | 136 |
| M5J | Downtown & Central Toronto | 31 days | 64 days | 300 |
| M8Z | Etobicoke (south) | 31 days | 238 days | 450 |
| M9C | Etobicoke & Northwest Toronto | 31 days | 135 days | 209 |
| M9N | Etobicoke & Northwest Toronto | 31 days | 387 days | 164 |
| M1T | Scarborough | 30 days | 126 days | 110 |
| M1X | Scarborough | 30 days | 476 days | 61 |
| M2N | North York (east) | 30 days | 113 days | 468 |
| M4A | East York, East Toronto & Midtown | 30 days | 108 days | 102 |
| M4H | East York, East Toronto & Midtown | 30 days | 272 days | 49 |
| M5B | Downtown & Central Toronto | 30 days | 121 days | 172 |
| M9R | Etobicoke & Northwest Toronto | 30 days | 146 days | 104 |
| M9V | Etobicoke & Northwest Toronto | 30 days | 212 days | 168 |
| M2L | North York (east) | 29 days | 115 days | 145 |
| M4V | East York, East Toronto & Midtown | 29 days | 106 days | 229 |
| M6K | West Toronto & York | 29 days | 191 days | 351 |
| M8Y | Etobicoke (south) | 29 days | 147 days | 226 |
| M9L | Etobicoke & Northwest Toronto | 29 days | 188 days | 105 |
| M1H | Scarborough | 28 days | 173 days | 133 |
| M1N | Scarborough | 28 days | 228 days | 292 |
| M4C | East York, East Toronto & Midtown | 28 days | 158 days | 574 |
| M4M | East York, East Toronto & Midtown | 28 days | 286 days | 384 |
| M4N | East York, East Toronto & Midtown | 28 days | 211 days | 224 |
| M5G | Downtown & Central Toronto | 28 days | 106 days | 248 |
| M5H | Downtown & Central Toronto | 28 days | 63 days | 368 |
| M6C | West Toronto & York | 28 days | 151 days | 390 |
| M3M | North York (west) | 27 days | 189 days | 107 |
| M4E | East York, East Toronto & Midtown | 27 days | 175 days | 299 |
| M5R | Downtown & Central Toronto | 27 days | 116 days | 470 |
| M2H | North York (east) | 26 days | 162 days | 126 |
| M4G | East York, East Toronto & Midtown | 26 days | 145 days | 333 |
| M4X | East York, East Toronto & Midtown | 26 days | 97 days | 85 |
| M6H | West Toronto & York | 26 days | 154 days | 709 |
| M2J | North York (east) | 25 days | 120 days | 221 |
| M9A | Etobicoke & Northwest Toronto | 25 days | 97 days | 334 |
| M1G | Scarborough | 24 days | 105 days | 92 |
| M4L | East York, East Toronto & Midtown | 24 days | 158 days | 506 |
| M2P | North York (east) | 23 days | 64 days | 91 |
| M5P | Downtown & Central Toronto | 23 days | 72 days | 235 |
| M6G | West Toronto & York | 23 days | 122 days | 582 |
| M6J | West Toronto & York | 23 days | 120 days | 553 |
| M6S | West Toronto & York | 23 days | 112 days | 455 |
| M4R | East York, East Toronto & Midtown | 22 days | 140 days | 187 |
| M8V | Etobicoke (south) | 22 days | 139 days | 362 |
| M8X | Etobicoke (south) | 22 days | 205 days | 146 |
| M4K | East York, East Toronto & Midtown | 21 days | 137 days | 460 |
| M6P | West Toronto & York | 21 days | 160 days | 529 |
| M6R | West Toronto & York | 19 days | 101 days | 420 |
| M4J | East York, East Toronto & Midtown | 18 days | 111 days | 507 |
| M5N | Downtown & Central Toronto | 18 days | 68 days | 184 |
| M4T | East York, East Toronto & Midtown | 15 days | 93 days | 209 |
Common questions
- How long does a building permit take in Toronto?
- Half of the 27,839 permits issued in Toronto over the last 12 months were issued within 32 days of application. One in ten took longer than 224 days. The wait varies sharply by trade: New build runs about 65 days while Window / Door runs about 12 days.
- Which part of Toronto approves permits fastest?
- Among the 96 postal areas with enough permits to measure, M4T has the shortest median wait at 15 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
- Why is the median used instead of the average?
- Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 99 days against a median of 32 days. The median is the honest answer to "how long will mine take".
How these numbers are calculated
Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.
We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 99 days against a median of 32.
One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.