PermitIndex

Reference

How long does a building permit take in Toronto?

Half of the 30,910 permits the City issued over the trailing 12 months came through within 29 days of application. One in ten took longer than 176 days. Which half you land in depends far more on what you are building than on where.

Median wait

29 days

Slowest 10%

176+ days

Permits measured

30,910

Postal areas

98

Wait time by trade

Slowest first. This is the single biggest driver of how long you will wait.

TradeMedianSlowest 10%Permits
New build58 days521 days2,937
Demolition43 days229 days1,633
HVAC34 days191 days4,644
Addition32 days166 days5,002
Electrical32 days92 days95
Pool32 days142 days172
Plumbing27 days232 days6,668
Roofing25 days124 days537
Interior alteration24 days91 days4,532
Deck21 days119 days1,529
Window / Door11 days61 days901

Wait time by postal area

The 98 Toronto postal areas with at least 30 measurable permits, slowest first.

AreaZoneMedianSlowest 10%Permits
M3CNorth York (west)233 days298 days546
M6NWest Toronto & York73 days883 days817
M1LScarborough57 days256 days368
M9MEtobicoke & Northwest Toronto44 days257 days136
M1CScarborough42 days1439 days314
M6AWest Toronto & York42 days611 days444
M5ADowntown & Central Toronto40 days273 days322
M8WEtobicoke (south)40 days133 days325
M7AQueen's Park39 days79 days50
M1BScarborough38 days197 days244
M1VScarborough38 days208 days182
M1JScarborough37 days281 days155
M1KScarborough37 days285 days247
M2MNorth York (east)36 days101 days359
M4BEast York, East Toronto & Midtown36 days153 days231
M5TDowntown & Central Toronto36 days210 days283
M6LWest Toronto & York36 days201 days161
M9WEtobicoke & Northwest Toronto36 days134 days365
M1EScarborough35 days190 days318
M1MScarborough35 days280 days274
M1WScarborough35 days142 days135
M2RNorth York (east)35 days223 days281
M3KNorth York (west)35 days121 days106
M6MWest Toronto & York35 days296 days287
M9BEtobicoke & Northwest Toronto35 days234 days320
M3JNorth York (west)34 days240 days156
M4YEast York, East Toronto & Midtown34 days93 days103
M5SDowntown & Central Toronto34 days126 days346
M4PEast York, East Toronto & Midtown33 days149 days244
M9PEtobicoke & Northwest Toronto33 days392 days110
M1SScarborough32 days178 days236
M2KNorth York (east)32 days856 days165
M5BDowntown & Central Toronto32 days153 days177
M5CDowntown & Central Toronto32 days61 days249
M3BNorth York (west)31 days142 days294
M3LNorth York (west)31 days99 days71
M4AEast York, East Toronto & Midtown31 days91 days116
M5VDowntown & Central Toronto31 days94 days475
M6BWest Toronto & York31 days145 days341
M9NEtobicoke & Northwest Toronto31 days391 days179
M9REtobicoke & Northwest Toronto31 days146 days139
M1PScarborough30 days116 days328
M1RScarborough30 days169 days335
M3ANorth York (west)30 days252 days166
M5JDowntown & Central Toronto30 days62 days317
M9VEtobicoke & Northwest Toronto30 days181 days175
M1HScarborough29 days149 days158
M1TScarborough29 days117 days136
M3HNorth York (west)29 days141 days338
M3NNorth York (west)29 days145 days66
M4NEast York, East Toronto & Midtown29 days217 days255
M4WEast York, East Toronto & Midtown29 days105 days392
M5GDowntown & Central Toronto29 days95 days292
M6EWest Toronto & York29 days155 days618
M8ZEtobicoke (south)29 days177 days508
M9LEtobicoke & Northwest Toronto29 days168 days101
M2NNorth York (east)28 days103 days555
M4HEast York, East Toronto & Midtown28 days219 days35
M4SEast York, East Toronto & Midtown28 days135 days411
M5EDowntown & Central Toronto28 days60 days95
M5MDowntown & Central Toronto28 days222 days384
M9CEtobicoke & Northwest Toronto28 days94 days266
M5HDowntown & Central Toronto27 days49 days480
M5XDowntown & Central Toronto27 days42 days37
M6KWest Toronto & York27 days191 days393
M6PWest Toronto & York27 days152 days602
M1NScarborough26 days202 days329
M2PNorth York (east)26 days82 days106
M3MNorth York (west)26 days166 days120
M4GEast York, East Toronto & Midtown26 days118 days390
M6CWest Toronto & York26 days127 days404
M4MEast York, East Toronto & Midtown25 days203 days467
M5RDowntown & Central Toronto25 days91 days511
M8XEtobicoke (south)25 days93 days171
M8YEtobicoke (south)25 days106 days273
M9AEtobicoke & Northwest Toronto25 days113 days339
M2HNorth York (east)24 days118 days150
M4CEast York, East Toronto & Midtown24 days89 days633
M4VEast York, East Toronto & Midtown24 days76 days248
M6HWest Toronto & York24 days127 days806
M8VEtobicoke (south)23 days161 days410
M4KEast York, East Toronto & Midtown22 days116 days516
M4LEast York, East Toronto & Midtown22 days128 days581
M4XEast York, East Toronto & Midtown22 days97 days96
M2LNorth York (east)21 days89 days148
M4EEast York, East Toronto & Midtown21 days169 days340
M4REast York, East Toronto & Midtown21 days96 days196
M5NDowntown & Central Toronto21 days93 days179
M5PDowntown & Central Toronto21 days82 days247
M6GWest Toronto & York21 days126 days629
M6JWest Toronto & York21 days118 days627
M6RWest Toronto & York21 days92 days477
M6SWest Toronto & York20 days113 days510
M2JNorth York (east)18 days85 days255
M4JEast York, East Toronto & Midtown18 days100 days596
M1XScarborough16 days194 days58
M1GScarborough15 days169 days163
M4TEast York, East Toronto & Midtown15 days83 days227

Common questions

How long does a building permit take in Toronto?
Half of the 30,910 permits issued in Toronto over the last 12 months were issued within 29 days of application. One in ten took longer than 176 days. The wait varies sharply by trade: New build runs about 58 days while Window / Door runs about 11 days.
Which part of Toronto approves permits fastest?
Among the 98 postal areas with enough permits to measure, M4T has the shortest median wait at 15 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
Why is the median used instead of the average?
Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 88 days against a median of 29 days. The median is the honest answer to "how long will mine take".

How these numbers are calculated

Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.

We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 88 days against a median of 29.

One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.