How long does a building permit take in Toronto?
Half of the 30,910 permits the City issued over the trailing 12 months came through within 29 days of application. One in ten took longer than 176 days. Which half you land in depends far more on what you are building than on where.
Median wait
29 days
Slowest 10%
176+ days
Permits measured
30,910
Postal areas
98
Wait time by trade
Slowest first. This is the single biggest driver of how long you will wait.
| Trade | Median | Slowest 10% | Permits |
|---|---|---|---|
| New build | 58 days | 521 days | 2,937 |
| Demolition | 43 days | 229 days | 1,633 |
| HVAC | 34 days | 191 days | 4,644 |
| Addition | 32 days | 166 days | 5,002 |
| Electrical | 32 days | 92 days | 95 |
| Pool | 32 days | 142 days | 172 |
| Plumbing | 27 days | 232 days | 6,668 |
| Roofing | 25 days | 124 days | 537 |
| Interior alteration | 24 days | 91 days | 4,532 |
| Deck | 21 days | 119 days | 1,529 |
| Window / Door | 11 days | 61 days | 901 |
Wait time by postal area
The 98 Toronto postal areas with at least 30 measurable permits, slowest first.
| Area | Zone | Median | Slowest 10% | Permits |
|---|---|---|---|---|
| M3C | North York (west) | 233 days | 298 days | 546 |
| M6N | West Toronto & York | 73 days | 883 days | 817 |
| M1L | Scarborough | 57 days | 256 days | 368 |
| M9M | Etobicoke & Northwest Toronto | 44 days | 257 days | 136 |
| M1C | Scarborough | 42 days | 1439 days | 314 |
| M6A | West Toronto & York | 42 days | 611 days | 444 |
| M5A | Downtown & Central Toronto | 40 days | 273 days | 322 |
| M8W | Etobicoke (south) | 40 days | 133 days | 325 |
| M7A | Queen's Park | 39 days | 79 days | 50 |
| M1B | Scarborough | 38 days | 197 days | 244 |
| M1V | Scarborough | 38 days | 208 days | 182 |
| M1J | Scarborough | 37 days | 281 days | 155 |
| M1K | Scarborough | 37 days | 285 days | 247 |
| M2M | North York (east) | 36 days | 101 days | 359 |
| M4B | East York, East Toronto & Midtown | 36 days | 153 days | 231 |
| M5T | Downtown & Central Toronto | 36 days | 210 days | 283 |
| M6L | West Toronto & York | 36 days | 201 days | 161 |
| M9W | Etobicoke & Northwest Toronto | 36 days | 134 days | 365 |
| M1E | Scarborough | 35 days | 190 days | 318 |
| M1M | Scarborough | 35 days | 280 days | 274 |
| M1W | Scarborough | 35 days | 142 days | 135 |
| M2R | North York (east) | 35 days | 223 days | 281 |
| M3K | North York (west) | 35 days | 121 days | 106 |
| M6M | West Toronto & York | 35 days | 296 days | 287 |
| M9B | Etobicoke & Northwest Toronto | 35 days | 234 days | 320 |
| M3J | North York (west) | 34 days | 240 days | 156 |
| M4Y | East York, East Toronto & Midtown | 34 days | 93 days | 103 |
| M5S | Downtown & Central Toronto | 34 days | 126 days | 346 |
| M4P | East York, East Toronto & Midtown | 33 days | 149 days | 244 |
| M9P | Etobicoke & Northwest Toronto | 33 days | 392 days | 110 |
| M1S | Scarborough | 32 days | 178 days | 236 |
| M2K | North York (east) | 32 days | 856 days | 165 |
| M5B | Downtown & Central Toronto | 32 days | 153 days | 177 |
| M5C | Downtown & Central Toronto | 32 days | 61 days | 249 |
| M3B | North York (west) | 31 days | 142 days | 294 |
| M3L | North York (west) | 31 days | 99 days | 71 |
| M4A | East York, East Toronto & Midtown | 31 days | 91 days | 116 |
| M5V | Downtown & Central Toronto | 31 days | 94 days | 475 |
| M6B | West Toronto & York | 31 days | 145 days | 341 |
| M9N | Etobicoke & Northwest Toronto | 31 days | 391 days | 179 |
| M9R | Etobicoke & Northwest Toronto | 31 days | 146 days | 139 |
| M1P | Scarborough | 30 days | 116 days | 328 |
| M1R | Scarborough | 30 days | 169 days | 335 |
| M3A | North York (west) | 30 days | 252 days | 166 |
| M5J | Downtown & Central Toronto | 30 days | 62 days | 317 |
| M9V | Etobicoke & Northwest Toronto | 30 days | 181 days | 175 |
| M1H | Scarborough | 29 days | 149 days | 158 |
| M1T | Scarborough | 29 days | 117 days | 136 |
| M3H | North York (west) | 29 days | 141 days | 338 |
| M3N | North York (west) | 29 days | 145 days | 66 |
| M4N | East York, East Toronto & Midtown | 29 days | 217 days | 255 |
| M4W | East York, East Toronto & Midtown | 29 days | 105 days | 392 |
| M5G | Downtown & Central Toronto | 29 days | 95 days | 292 |
| M6E | West Toronto & York | 29 days | 155 days | 618 |
| M8Z | Etobicoke (south) | 29 days | 177 days | 508 |
| M9L | Etobicoke & Northwest Toronto | 29 days | 168 days | 101 |
| M2N | North York (east) | 28 days | 103 days | 555 |
| M4H | East York, East Toronto & Midtown | 28 days | 219 days | 35 |
| M4S | East York, East Toronto & Midtown | 28 days | 135 days | 411 |
| M5E | Downtown & Central Toronto | 28 days | 60 days | 95 |
| M5M | Downtown & Central Toronto | 28 days | 222 days | 384 |
| M9C | Etobicoke & Northwest Toronto | 28 days | 94 days | 266 |
| M5H | Downtown & Central Toronto | 27 days | 49 days | 480 |
| M5X | Downtown & Central Toronto | 27 days | 42 days | 37 |
| M6K | West Toronto & York | 27 days | 191 days | 393 |
| M6P | West Toronto & York | 27 days | 152 days | 602 |
| M1N | Scarborough | 26 days | 202 days | 329 |
| M2P | North York (east) | 26 days | 82 days | 106 |
| M3M | North York (west) | 26 days | 166 days | 120 |
| M4G | East York, East Toronto & Midtown | 26 days | 118 days | 390 |
| M6C | West Toronto & York | 26 days | 127 days | 404 |
| M4M | East York, East Toronto & Midtown | 25 days | 203 days | 467 |
| M5R | Downtown & Central Toronto | 25 days | 91 days | 511 |
| M8X | Etobicoke (south) | 25 days | 93 days | 171 |
| M8Y | Etobicoke (south) | 25 days | 106 days | 273 |
| M9A | Etobicoke & Northwest Toronto | 25 days | 113 days | 339 |
| M2H | North York (east) | 24 days | 118 days | 150 |
| M4C | East York, East Toronto & Midtown | 24 days | 89 days | 633 |
| M4V | East York, East Toronto & Midtown | 24 days | 76 days | 248 |
| M6H | West Toronto & York | 24 days | 127 days | 806 |
| M8V | Etobicoke (south) | 23 days | 161 days | 410 |
| M4K | East York, East Toronto & Midtown | 22 days | 116 days | 516 |
| M4L | East York, East Toronto & Midtown | 22 days | 128 days | 581 |
| M4X | East York, East Toronto & Midtown | 22 days | 97 days | 96 |
| M2L | North York (east) | 21 days | 89 days | 148 |
| M4E | East York, East Toronto & Midtown | 21 days | 169 days | 340 |
| M4R | East York, East Toronto & Midtown | 21 days | 96 days | 196 |
| M5N | Downtown & Central Toronto | 21 days | 93 days | 179 |
| M5P | Downtown & Central Toronto | 21 days | 82 days | 247 |
| M6G | West Toronto & York | 21 days | 126 days | 629 |
| M6J | West Toronto & York | 21 days | 118 days | 627 |
| M6R | West Toronto & York | 21 days | 92 days | 477 |
| M6S | West Toronto & York | 20 days | 113 days | 510 |
| M2J | North York (east) | 18 days | 85 days | 255 |
| M4J | East York, East Toronto & Midtown | 18 days | 100 days | 596 |
| M1X | Scarborough | 16 days | 194 days | 58 |
| M1G | Scarborough | 15 days | 169 days | 163 |
| M4T | East York, East Toronto & Midtown | 15 days | 83 days | 227 |
Common questions
- How long does a building permit take in Toronto?
- Half of the 30,910 permits issued in Toronto over the last 12 months were issued within 29 days of application. One in ten took longer than 176 days. The wait varies sharply by trade: New build runs about 58 days while Window / Door runs about 11 days.
- Which part of Toronto approves permits fastest?
- Among the 98 postal areas with enough permits to measure, M4T has the shortest median wait at 15 days and M3C has the longest at 233 days. Area differences mostly reflect what is being built there rather than the office handling it, since project type drives the wait far more than geography.
- Why is the median used instead of the average?
- Permit waits have a long tail: a small number of complex projects take years and drag the average far above what a typical applicant experiences. The citywide average is 88 days against a median of 29 days. The median is the honest answer to "how long will mine take".
How these numbers are calculated
Each permit’s wait is the number of days between its application date and its issue date, both as recorded by the City of Toronto. We include permits issued in the trailing 12 months, drop records where the issue date precedes the application date, and report a group only when it contains at least 30 permits. Fewer than that and a median is noise.
We publish medians rather than averages. A handful of very large projects take years and pull the average well above what a typical applicant sees: 88 days against a median of 29.
One important limitation: the City’s open dataset covers active permits, so records leave it as projects close out. That means this measures permits currently on record, not a complete historical census, and it is why we restrict the window to 12 months where coverage is most complete. It describes permits already issued and is not a processing commitment from the City. For the official process, see the data sources page.