2017 permits

Toronto building permits from 2017: 8,643 are still open

Of the building permits Toronto issued in 2017, 8,643 remained in the City’s active permit register, and half of them have been open for at least 3,319 days (about 9 years).

This is not annual permit volume. The 2017 figures on this page count permits that are still openin the City of Toronto’s active permit register today. Permits drop out of that register once they close, so older years show fewer surviving records the further back you go. Toronto issues roughly 30,000 to 40,000 permits a year; the counts here are the unclosed remainder, and they cannot be compared between years as a trend.

Still open

8,643

Median time open

3,319 d

Median value

$100,000

Total value

$3,328,907,415

Value figures cover the 4,440 of 8,643 still-open 2017 permits that disclose an estimated construction cost. Medians, not averages: the cost distribution has a long tail and an average would overstate the typical permit.

What stage the 2017 permits are at

1,474 of them (17.1%) show no sign of work having begun: the permit was issued and the file has not moved past that point.

StatusPermitsShare
Inspection
5,923
68.5%
Permit Issued
1,429
16.5%
Revision Issued
870
10.1%
Revocation Pending
375
4.3%
Work Not Started
45
0.5%
Work Suspended
1
0.0%

Still-open 2017 permits by trade

TradePermitsTotal value
Plumbing1,755$55,727,061
Interior alteration1,602$377,938,450
Addition1,497$488,034,294
New build1,152$1,891,684,162
HVAC1,120$142,108,120
Other / unclassified467$65,319,478
Deck336$45,365,094
Roofing286$83,793,810
Window / Door203$66,686,102
Demolition166$85,094,069
Pool38$5,311,500
Electrical21$21,845,275

Neighbourhoods with the most open 2017 permits

RankNeighbourhoodOpen permitsTotal value
1Downsview546$54,114,760
2East L'Amoreaux305$60,906,960
3Yonge-Bay Corridor258$195,111,015
4Annex200$187,651,120
5West Humber-Clairville175$59,753,956
6South Riverdale174$10,260,458
7Kensington-Chinatown166$299,831,291
8High Park-Swansea139$23,631,699
9Etobicoke City Centre132$20,515,130
10Mimico-Queensway128$27,485,000
11Bay-Cloverhill122$116,838,690
12York University Heights117$18,310,120
13Wellington Place115$22,411,564
14Stonegate-Queensway108$34,146,194
15St Lawrence-East Bayfront-The Islands106$228,412,120
16High Park North104$7,982,500
17Wexford/Maryvale103$5,573,868
18Trinity-Bellwoods103$56,788,400
19Rosedale-Moore Park103$27,598,900
20Banbury-Don Mills101$27,488,115

Top 20 neighbourhoods by open-permit count. Areas outside this list still have open 2017 permits.

Largest 2017 projects still open

The highest-value permits from 2017 that have not closed out, ranked by estimated construction cost.

AddressWorkStatusOpenValue
600 University Ave, Toronto, ONMultiple ProjectsInspection3,373 d$244,500,000
12 Bonnycastle St, Toronto, ONNew BuildingInspection3,163 d$131,800,000
43 Gerrard St W, Toronto, ONNew BuildingInspection3,370 d$125,000,000
50-60 Charles St E, Toronto, ONNew BuildingInspection3,159 d$114,738,000
511 Bremner Blvd, Toronto, ONNew BuildingInspection3,395 d$110,000,000
460 Yonge St, Toronto, ONNew BuildingInspection3,465 d$100,000,000
1 Dartnell Ave, Toronto, ONOther(MS)Inspection3,362 d$95,000,000
2384 Yonge St, Toronto, ONNew BuildingInspection3,333 d$80,000,000
55 St George St, Toronto, ONNew BuildingInspection3,374 d$77,256,000
135 Yorkville Ave, Toronto, ONNew BuildingInspection3,380 d$75,000,000
188 Cumberland St, Toronto, ONNew BuildingInspection3,318 d$75,000,000
110 River St, Toronto, ONNew BuildingInspection3,293 d$75,000,000
210 Eastern Ave, Toronto, ONNew BuildingInspection3,369 d$68,000,000
410 Bathurst St, Toronto, ONNew BuildingInspection3,198 d$53,000,000
50 Regent Park Blvd, Toronto, ONNew BuildingInspection3,146 d$42,000,000
1265 Military Trl, Toronto, ONAddition(s)Inspection3,159 d$38,200,000
125 Parkway Forest Dr, Toronto, ONNew BuildingPermit Issued3,220 d$37,000,000
48 Abell St, Toronto, ONNew BuildingInspection3,146 d$36,000,000
200 Sackville St, Toronto, ONNew BuildingInspection3,214 d$34,500,000
1555 Midland Ave, Toronto, ONNew BuildingInspection3,403 d$32,000,000
3-5 Allenbury Gdns, Toronto, ONNew BuildingInspection3,368 d$31,000,000
925 Dixon Rd, Toronto, ONMultiple ProjectsInspection3,397 d$30,000,000
927 A Eglinton Ave W, Toronto, ONNew BuildingInspection3,397 d$27,000,000
555 Finch Ave W, Toronto, ONNew BuildingInspection3,163 d$23,000,000
3080 Yonge St, Toronto, ONMultiple ProjectsInspection3,306 d$20,000,000

“Open” counts days from issue date to Jul 23, 2026. A permit remaining open does not by itself mean a project is abandoned; the City closes permits on final inspection, and some long-running projects are still legitimately active.

Track new Toronto permits the day they are issued. Historical pages show what is still open. Sign in free to see what was filed this morning.

Frequently asked questions

How many Toronto building permits from 2017 are still open?
8,643 permits issued in Toronto during 2017 were still in the City's active permit register. This is the count of permits that have not closed out, not the number of permits Toronto issued in 2017. The City issues roughly 30,000 to 40,000 permits a year, and closed permits are removed from the published file.
How long have Toronto's 2017 permits been open?
Half of the 8,643 still-open permits from 2017 have been open for at least 3,319 days (about 9 years), measured from issue date to Jul 23, 2026. One in ten has been open longer than 3,452 days (about 9 years). These are permits the City has not closed out, which can mean a long-running project, a stalled one, or one that was finished without being signed off.
How many 2017 Toronto permits were never started?
1,474 of the 8,643 surviving 2017 permits (17.1%) sit at a status indicating work has not visibly begun, such as "Permit Issued" or "Work Not Started". The approval was granted and the file shows no progression past it. The remainder are at inspection or revision stages.
Can I compare 2017 to other years?
No. Each year's count reflects how long its permits have had to close, so an older year showing fewer permits means more of them closed, not that less was built. Comparing 2017 to another year measures elapsed time rather than construction activity. Use the status and trade breakdowns within 2017 instead.