PermitIndex

2008 permits

Toronto building permits from 2008: 4,987 are still open

Of the building permits Toronto issued in 2008, 4,987 remained in the City’s active permit register, and half of them have been open for at least 6,600 days (about 18 years).

This is not annual permit volume. The 2008 figures on this page count permits that are still openin the City of Toronto’s active permit register today. Permits drop out of that register once they close, so older years show fewer surviving records the further back you go. Toronto issues roughly 30,000 to 40,000 permits a year; the counts here are the unclosed remainder, and they cannot be compared between years as a trend.

Still open

4,987

Median time open

6,600 d

Median value

$50,000

Total value

$1,822,991,191

Value figures cover the 2,453 of 4,987 still-open 2008 permits that disclose an estimated construction cost. Medians, not averages: the cost distribution has a long tail and an average would overstate the typical permit.

What stage the 2008 permits are at

161 of them (3.2%) show no sign of work having begun: the permit was issued and the file has not moved past that point.

StatusPermitsShare
Inspection
4,337
87.0%
Revision Issued
482
9.7%
Permit Issued
106
2.1%
Work Not Started
55
1.1%
Revocation Pending
7
0.1%

Still-open 2008 permits by trade

TradePermitsTotal value
Addition1,209$136,530,561
Interior alteration852$264,971,192
Plumbing819$8,317,155
HVAC692$40,424,000
New build474$1,201,872,253
Deck301$12,403,500
Other / unclassified267$25,059,520
Roofing140$52,379,440
Demolition103$58,583,800
Window / Door103$6,284,854
Pool22$3,790,000
Electrical5$12,374,917

Neighbourhoods with the most open 2008 permits

RankNeighbourhoodOpen permitsTotal value
1Stonegate-Queensway209$13,220,100
2Rosedale-Moore Park143$9,528,391
3Bedford Park-Nortown140$16,503,062
4Yonge-Bay Corridor135$130,973,245
5O'Connor-Parkview126$6,877,000
6West Humber-Clairville125$25,857,500
7South Riverdale116$83,679,200
8High Park-Swansea93$5,644,600
9Annex91$8,547,270
10Leaside-Bennington85$6,223,600
11North Riverdale80$1,712,000
12Palmerston-Little Italy75$14,187,000
13Kensington-Chinatown74$127,434,516
14Runnymede-Bloor West Village74$2,094,070
15The Beaches72$6,956,000
16Mimico-Queensway72$10,171,289
17Edenbridge-Humber Valley71$10,704,000
18Lawrence Park South65$6,231,300
19Islington63$3,766,600
20Humewood-Cedarvale62$4,982,300

Top 20 neighbourhoods by open-permit count. Areas outside this list still have open 2008 permits.

Largest 2008 projects still open

The highest-value permits from 2008 that have not closed out, ranked by estimated construction cost.

AddressWorkStatusOpenValue
15 York St, Toronto, ONNew BuildingInspection6,664 d$325,000,000
200 Front St W, Toronto, ONNew BuildingInspection6,509 d$200,000,000
209 Victoria St, Toronto, ONNew BuildingInspection6,764 d$97,000,000
550 University Ave, Toronto, ONMultiple ProjectsInspection6,603 d$87,913,016
70 Birmingham St, Toronto, ONNew BuildingInspection6,757 d$65,000,000
40 King St W, Toronto, ONMultiple ProjectsWork Not Started6,756 d$50,000,000
33 Bay St, Toronto, ONNew BuildingInspection6,762 d$40,000,000
4 A Spadina Ave, Toronto, ONNew BuildingInspection6,616 d$40,000,000
201 Carlaw Ave, Toronto, ONNew BuildingInspection6,426 d$40,000,000
510 St Clair Ave W, Toronto, ONNew BuildingInspection6,530 d$35,000,000
1042-1048 Broadview Ave, Toronto, ONNew BuildingInspection6,526 d$35,000,000
1070 Sheppard Ave W, Toronto, ONNew BuildingInspection6,420 d$31,520,000
5793 Yonge St, Toronto, ONNew BuildingInspection6,426 d$26,000,000
519 Dundas St W, Toronto, ONOther(BA)Inspection6,736 d$25,000,000
60 Queen St W, Toronto, ONMultiple ProjectsInspection6,691 d$25,000,000
20 Gothic Ave, Toronto, ONNew BuildingInspection6,561 d$25,000,000
27 Rean Dr, Toronto, ONNew BuildingInspection6,460 d$24,000,000
825 Dundas St E, Toronto, ONNew BuildingInspection6,491 d$23,000,000
65 Lillian St, Toronto, ONNew BuildingInspection6,462 d$22,500,000
872 Sheppard Ave W, Toronto, ONNew BuildingInspection6,474 d$20,500,000
5793 Yonge St, Toronto, ONNew BuildingInspection6,426 d$20,290,000
4600 Bathurst St, Toronto, ONAddition(s)Inspection6,649 d$15,000,000
1 Dundas St W, Toronto, ONChange of UseInspection6,540 d$13,500,000
825 Dundas St E, Toronto, ONNew BuildingInspection6,702 d$9,000,000
2603 Bathurst St, Toronto, ONInterior AlterationsInspection6,575 d$9,000,000

“Open” counts days from issue date to Jul 23, 2026. A permit remaining open does not by itself mean a project is abandoned; the City closes permits on final inspection, and some long-running projects are still legitimately active.

Track new Toronto permits the day they are issued. Historical pages show what is still open. Sign in free to see what was filed this morning.

Frequently asked questions

How many Toronto building permits from 2008 are still open?
4,987 permits issued in Toronto during 2008 were still in the City's active permit register. This is the count of permits that have not closed out, not the number of permits Toronto issued in 2008. The City issues roughly 30,000 to 40,000 permits a year, and closed permits are removed from the published file.
How long have Toronto's 2008 permits been open?
Half of the 4,987 still-open permits from 2008 have been open for at least 6,600 days (about 18 years), measured from issue date to Jul 23, 2026. One in ten has been open longer than 6,733 days (about 18 years). These are permits the City has not closed out, which can mean a long-running project, a stalled one, or one that was finished without being signed off.
How many 2008 Toronto permits were never started?
161 of the 4,987 surviving 2008 permits (3.2%) sit at a status indicating work has not visibly begun, such as "Permit Issued" or "Work Not Started". The approval was granted and the file shows no progression past it. The remainder are at inspection or revision stages.
Can I compare 2008 to other years?
No. Each year's count reflects how long its permits have had to close, so an older year showing fewer permits means more of them closed, not that less was built. Comparing 2008 to another year measures elapsed time rather than construction activity. Use the status and trade breakdowns within 2008 instead.

Other years